University of Tennessee Stokely Athletic Center & Gibbs Hall

EAI performed asbestos abatement of the former athletic facility/indoor track prior to the demolition of the facilities.  Scope of work included abatement of structural fireproofing (>150,000 SF), thermal system insulation (>15,000 LF), floor tile/mastic (approx. 50,000 SF) as well as the removal of bulbs, ballast and mercury switches.  The uniqueness of the project included:

- Integrate decked scaffolding system accessing the fireproofing adhered to structural columns

- Elaborate containment system enveloping the designated work areas

- Extensive interior CMU all demolition to access structural members/ fireproofing

- Extensive demolition to access thermal system piping (elevated & below grade

- Completion of project 3 weeks ahead of schedule